Against the backdrop of the snowy pre-Alps, workers on the roof of the Cryostat Workshop in February position large pieces of aluminum cladding.
2014-02-03 - On the southern end of the Seismic Pit, two of the three basemat segments are in place and the third will be filled in mid-February. Concrete pouring activity will then be transferred to the opposite side.
2014-01-29 - The seven-level Tokamak Building, which will house the machine and auxiliary systems, will sit five storeys (60 metres) above ground and two below.