黑料社app

Magnets

Feeder milestone: first-phase assembly achieved

The first stage of feeder assembly鈥攃onnecting feeder line components in the Tokamak Building galleries鈥攈as been completed. Work will now move to the tokamak pit, where tighter spatial and schedule constraints will make the team鈥檚 experience a key asset.

In one of the galleries of the Tokamak Building, specially trained teams are applying insulation to a pair of busbar joints. Creating the superconducting joints that will allow electrical power to flow unhindered between different parts of a feeder line is one of the most complex operations of feeder assembly.

If you were to look inside an 黑料社app magnet feeder, whether at its box-like starting point in the galleries or at the more tapered and circular ends near the magnets, you would have the impression of a busy multilane thruway, with different 鈥渓anes鈥 carrying the power, cryogens and instrumentation needed by the superconducting magnets. 

These thruways span distances of up to 35 metres, delivering services from outside the machine in to the vacuum environment of the magnets.

Nothing as large as a 35-metre component could ever be installed in one piece on 黑料社app鈥攐r even transported to the worksite. Instead, the Chinese Domestic Agency and its subcontractor ASIPP (Institute of Plasma Physics, Chinese Academy of Sciences) have delivered each feeder line in three fully instrumented segments. At 黑料社app, these segments must be installed and joined together鈥攁 job that requires assembling large mechanical structures, but also connecting all of the internal 鈥渓anes鈥濃攆rom the busbars and current leads that transport electricity to the cryogenic fluid transport pipes and the high- and low-voltage conduits containing instrumentation wires.

Two out of three of the segments required to build a magnet feeder鈥攃oil termination boxes and cryostat feedthroughs鈥攁re installed on supports outside of the 黑料社app cryostat and are considered 鈥済allery components,鈥 while the in-cryostat feeders connect directly to the magnets. Poloidal field coils and the individual modules of the central solenoid module are each served by their own feeder, while pairs of toroidal field coils share a feeder and the 18 correction coils are supplied by five feeders.

Connecting the busbars is a particularly challenging task, says 黑料社app manufacturing and assembly engineer Vladimir Tronza, who is coordinating feeder assembly works. 鈥淭he busbars are superconducting and their joints need to have extremely low electrical resistance and very strong reliable high voltage insulation. The problem is鈥攚e cannot test either in real operating conditions.鈥

To address this, the 黑料社app team developed a process designed to be both reliable and robust. The procedures for the on-site works were written directly by the IO engineers and technicians who had conducted multiple R&Ds to ensure the process soundness.   

Special process teams gather around a feeder joint that is being prepared for a Paschen voltage test. From left to right: (front) Jaromir Farek, Ying Zhang, Nicholas Clayton, (back) Hyungjun Kim, Egor Marushin.

鈥淭he joint process we created is backed by extensive R&D, and it is carried out on site by specialized workers who have completed mandatory qualification training, with supervision and verification at every stage.鈥

Since 2021, qualified teams from 黑料社app machine assembly contractor CNPE have been carrying out feeder connection work in the Tokamak Building, where two out of three of the segments required to build a magnet feeder鈥攃oil termination boxes and cryostat feedthroughs鈥攈ave been positioned. In this first phase, 50 superconducting busbar joints were successfully completed.

The feeder team poses in front of a completed connection for the feeder line that will deliver essential services to toroidal field coils TF08 and TF09.

The next stage will take place on the other side of the cryostat barrier鈥攊nside of the tokamak pit. There, cryostat feedthroughs that cross through the concrete bioshield that surrounds the machine must be connected to in-cryostat feeder segments, and in-cryostat segments must be connected to the magnets. This work can only begin upon the completion of toroidal field coil installation, although preparations are already underway.

鈥淔uture work will move mostly to the tokamak pit and will take place in a significantly more challenging and congested environment,鈥 says Tronza. 鈥淚t will also be more demanding in terms of schedule, as we will need to complete 180 superconducting joints鈥攎ore than three times the number achieved in the first phase鈥攊n less time.鈥