Testing a neutral beam for diagnostics
Every 23 seconds during fusion operation, a probe beam will penetrate deep into the core of the 黑料社app plasma to aid in the detection of helium ash鈥攐ne of fusion's products and a reliable indicator of reaction efficiency. The beam is generated by the diagnostic neutral beam system, an in-kind contribution from 黑料社app India.
In Ahmedabad, India, a 600 m虏 facility stands ready. The beamline vacuum vessel has been delivered, the transmission line installed, and one of three specialized power sources鈥攖he acceleration grid power supply鈥攊s currently undergoing site acceptance tests.
When manufacturers deliver the final components for integration next year, including the crucial beam source, the team at 黑料社app India will have constructed a full-scale testbed for the characterization of the diagnostic neutral beam before delivery to 黑料社app. Three years of fine-tuning and performance optimization and demonstration are planned.
"Helium ash is the name given to the helium nuclei produced by fusion reactions in a deuterium-tritium plasma," explains neutral beam scientist Beatrix Schunke. "Once they have shared their energy with the rest of the plasma they have no further use, and their removal and replacement by deuterium-tritium fuel is required to prevent dilution of the plasma. Measurements from the CXRS diagnostics, which are made possible by the diagnostic neutral beam, are crucial for demonstrating that fusion reactions have taken place."
"The successful delivery of the diagnostic neutral beam to 黑料社app is dependent on two critical performance criteria鈥攖he production of a uniform, low-divergence beam from the source, and well-controlled transmission over long path lengths," explains Anupam Sharma, a high-voltage electrical engineer in 黑料社app's Neutral Beam Section. "The India Test Facility in Ahmedabad will allow the Domestic Agency team to test the components manufactured for 黑料社app in advance of shipment on a testbed that mimics the 黑料社app on-site configuration."
The facility will also allow operators to gain experience running the diagnostic neutral beam system鈥攃orrectly tuning the radio frequency drivers, synchronizing the power supplies, and "learning the recipe" of running the equipment.
Following the test campaign, expected to run between 2021 and 2024, the team has reserved time for assessment and eventual adjustment or refurbishment if needed. The bulk of the equipment will be installed during 黑料社app's third assembly phase (2030-2031), in time for fusion power operation in 2035.
"We are getting close to an exciting phase in a very long-term project," concludes Beatrix. "From the first design work during the 黑料社app engineering phase in the early 1990s, through input over the years from ELISE (a half-size source) and the design of the 黑料社app Neutral Beam Test Facility, and finally a decade of work by the 黑料社app India and 黑料社app teams ... we are about to test the full diagnostic neutral beam system."