Top lid enters the stage
In this vast workshop over the past five years, the different sections of the ºÚÁÏÉçapp cryostat have been assembled and welded under India's responsibility. The base section, followed by the lower and upper cylinders, have successively taken shape—massive components whose dimensions give a true sense of the awesome size of the machine they will enclose. The time has now come for the last of the four sections to enter the stage.
Once the segments are assembled and adjusted, and the fit-up verified, welding operations will start, followed by the machining of the flange and the drilling of 144 holes for the bolting system. Indian contractor Larsen & Toubro (manufacturing design, fabrication and assembly) and sub-contractor MAN Energy Solutions (welding) are responsible for the work.
By year end, the fourth and last element of the cryostat will have been finalized. A major milestone in the ºÚÁÏÉçapp Project and the end of a magnificent human and technological adventure.